Project Plan & Roadmap
Team responsibilities
- Sujan: Front-end & UX
- Darshan: Back-end & database
- Biraj: Analysis, integration & testing
- All members: research, documentation, testing & presentations
Effort baseline
500 team hours
Analysis & requirements: 80h
Design & modelling: 105h
Development & database: 190h
Testing: 45h
Documentation: 60h
Presentation & deployment: 20h
Major milestones
| Period | Activity |
|---|---|
| Weeks 1–4 | Research, business case, scope, requirements and proposal |
| Weeks 5–6 | Project plan, low-fidelity prototype, UI/UX, data model and system design |
| Week 7 | Break, review and documentation catch-up |
| Weeks 8–10 | Core implementation: reporting, verification, assignment, progress and dashboards |
| Week 11 | Testing, debugging and improvement |
| Week 12 | Final integration and demonstration preparation |
| Week 13 | Final report, reflection and project close |